Project Overview

T-Mobile 4 Newport to 5 Newport Bridge

Post-Tensioning Solutions de-stressed and re-anchored 20 post-tension tendons at T-Mobile’s Bellevue campus, enabling the successful addition of a new skybridge without major slab reconstruction.

Details

  • Controlled de-stressed and re-anchored 20 live tendons across two adjoining buildings.
  • Created opening for new building-to-building skybridge without slab replacement.
  • Used precision methods to maintain PT system performance post-modification.
  • Minimized construction disruption to occupied structures.
  • Coordinated with structural engineers to meet project specifications.

PT Modification

Tendon Re-anchoring

Structure

Skybridge Connection

Challenge

Live Structure Occupancy

Project Date

12-2020

T-Mobile Skybridge PT Work - Exposed Tendons
T-Mobile Tendon Anchoring
T-Mobile Skybridge Construction
image
image
image
image
image
image
image
image
image
image
Heading Icon
Company Porjects

Related Projects

Intel Hillsboro Parking Garage

Intel Hillsboro Parking Garage

Barrier Cable System – Installed and stressed 98,000 linear feet of vehicle barrier cable and 5,250 anchors.

Kirkland Urban

Kirkland Urban

Performed two major slab retrofits, including stairwell openings, skylight installation, and elevator expansion by de-tensioning and relocating tendons.